Wednesday, 16 February 2022

Study Tips to Ace PRINCE2 Agile Foundation Exam in 2022

prince2 agile foundation exam questions, prince2 agile foundation exam questions and answers pdf, prince2 agile foundation mock exam, prince2 agile foundation syllabus, prince2 agile foundation exam questions and answers, prince2 agile foundation exam dump, prince2 agile foundation exam simulator, prince2 agile foundation practice exam questions and answers, prince2 agile foundation exam, agile foundation exam questions and answers, agile foundation exam questions and answers pdf

PRINCE2 Agile Foundation is designed for individuals new to PRINCE2 and working in or around an agile project environment.

The PRINCE2 Agile Foundation Certification combines agile concepts with the world’s most famous project management system. This certification aids in learning agile methods, techniques, and approaches for structure, governance, and control. Project managers are growing in the job market by employing efficient, agile methods and highly efficient agile environments and agile teams. This has given many top organizations and companies a compelling reason to hire more project managers.

As a result, holding this certification can help you gain advanced agile and project management skills, paving the way for a successful future.

Tips for a Successful PRINCE2 Agile Foundation Exam

1. Study the PRINCE2 Agile Foundation Exam Thoroughly

Go through the entire PRINCE2 Agile Foundation course, the numerous exercises tests, and solve the sample papers. By solving the sample examination papers, you will get an idea of the areas that require improvement. This will also utilize the exam format and make you more confident. You must gain sufficient knowledge of the Agile methodology, which is the key to passing the Foundation exam on the first attempt.

2. Making A Proper Preparation Plan

PRINCE2 Agile Foundation certification can get a little complicated. Sometimes, you might feel that you are not obtaining sufficient time to prepare and make a Proper preparation plan, of course!

While you create an appropriate study plan for your PRINCE2 Agile Foundation certification, you need to take care of two things first, your study material and determining your priorities. Now, set up your preferences, make a list of all you require to cover, and there you go!

Also, do not forget to check the pre-requisites for the certification required. And try to brush up on those lessons before you kick start with your PRINCE2 Agile Foundation preparations.

3. Read the Question, Read the Answers, Answer the Question

Watch out for definitive answers such as All, Always, Never, Must, and Only. PRINCE2 is a methodology that requires applied adequately given the circumstances, avoiding any absolute responses unless it is a negative question, and selecting solutions that can be solved as generally/typically. Remember the Agile Foundation exam practice of the process of elimination you should be able to eliminate the incorrect and focus on looking for the best correct answer given the scenario.

4. Remember It Is a PRINCE2 Agile Foundation Exam

Answer following PRINCE2, not what your existing workplace project management approach may recommend. Remember that you may be practicing project management outside of the exam room, but you would typically do it not necessarily the PRINCE2 way. As such, remember for a reason to be true in an argument/reason question, it must be a PRINCE2 reason, not a common-sense reason.

5. Give Yourself the Best Event at Passing

Seriously consider attending one of the PRINCE2 courses. There is no better way to prepare, assuring that you have covered all the required material and understood it!

6. Join Forum

Many support groups and forums are available on the web for candidates taking up the PRINCE2 Agile Foundation Exam. You can find the Support Group on LinkedIn and other study groups, consisting of active members who have written the exam or are planning to give it soon. With the use of this platform, you can pursue help to understand the complex concepts for you, and in return, you can answer questions in the concepts that you find easy to solve. These groups are helpful for anyone writing the examination for the first time.

It does not matter if you have 100 different study materials or spent 100 hours preparing for the exam. The only things that matter are the number of concepts you comprehend and the quality of your learning in the hours you spend. These essential factors make a difference in the Agile Foundation exam. Confirm that you do not study new concepts in the eleventh hour as this will only lead to confusion and not better results.

Conclusion

We hope you discover this guide to passing the PRINCE2 Agile Foundation exam to achieve the certification. Success in the PRINCE2 Agile Foundation exam needs a combination of good exam techniques and detailed knowledge of how it works. Although the exam may sound daunting, you should feel reassured that all questions are multiple-choice and have high pass rates.

Study hard, complete PRINCE2 Agile Foundation sample questions, and feel secure about your passing opportunities!

Monday, 14 February 2022

Why Understanding Risks Improves Your Decision-making

ITSM, ITSM Exam Prep, ITSM Exam Preparation, ITSM Skills, ITSM Jobs, ITSM

Your organization’s ability to act is directly linked to its decision-making. In projects and (agile) development, decision-making is essential in driving delivery. That’s why most agile and project methodologies recommend securing decision authority as close to the “source” – where the actual work is done, e.g. at team/team member-level. Decision-making is such a critical component that any decision-making is to be encouraged as long as you learn and adapt based on the outcome. And here there’s an important link to understanding risks.

Your risks are a great place to start if you want a better understanding of your organization’s decision-making. Organizations might have several other types of risks: cybersecurity risks, compliance risks, or personal safety risks – often in different risk registers and systems, sometimes all lumped together in a big ol’ puddle without any means of discerning which type is which (this is not recommended). However, the risks covered in this article are what you’d traditionally call project risks. They’re events or matters that have a certain probability of making a particular impact on your ability to deliver a certain product.

When organizations are using SAFe or perhaps scrum with some traditional method on top, there’s also the inevitable discussion of impediments vs. risks (perhaps vs. enablers vs. issues vs. etc.). This could be a whole other discussion (perhaps Diogenes-bald-chicken-reminiscent) and is also not the subject of this article (which is about understanding risks).

CRASH COURSE: Risk Handling Methodology

Before going further into the understanding risks vs. decision-making ability you’ll also need a quick introduction to handling risks. There are different ways to handle risks depending on the agile framework you’re using. SAFe uses the ROAM method at PI-planning events (Planning Iteration – basically quarterly planning across products and the teams working on them). All teams identify risks that might impede their ability to deliver as agreed at the end of the iteration. Risks are talked through with “management” (= typically the business owner, but generally the people ordering deliveries in/changes to a product together with any facilitators, e.g. the Release Train Engineer in SAFe) in a ROAM session at the PI-event.

ROAM is an acronym, labeling how a certain risk is handled:

◉ Resolved

◉ Owned

◉ Accepted

◉ Mitigated

Starting from the bottom in understanding risks…

Mitigated risks have a plan for being implemented in the iteration. The plan is typically incepted in a combination of suggestions from the team and input from the ROAM session. The team and management agree on the mitigation plan.

Accepted risks are seen as conditions that might impact the delivery. It is, however, crucial for the team to understand the details of the risk and the possible impact.

Owned risks should be handled just like their Mitigated siblings, but no plan could be decided on before/at the session which is why “somebody” – the owner – has the unenviable task of figuring out how to handle it. Hopefully, there are processes and people in place to help owners manage these risks!

Resolved risks are sufficiently handled (mitigated or removed) during the ROAM session or at the planning event (at the latest) making the team confident that they won’t impact their ability to deliver as agreed.

Most organizations use variants on this method for labeling what is going to happen with a particular risk. Some organizations have even implemented “auto-labeling” for their risk handling based on their “category” as a function of consequence and probability – a practice that can be found in several methodologies. My experience is that, while auto-labeling can be a powerful decision-support and prioritization tool, full autopilot in this regard (e.g. accepting all risks in a certain category) is not recommended for understanding risks.

Your risk register tells you different things about your decision-making. Start by sorting out any “non-risks” such as a lack of resources (money or manpower) or other similar constraints that should either be remedied or accepted as conditions (and delivery expectations managed accordingly). The remaining risks and how your (project/agile) organization has decided to handle them, often tell different things about your decision-making.

This does have some active risk management as a prerequisite:

1. Someone follows up on the risks, e.g. making sure they’re closed when deemed irrelevant (= they’re 

2. not visible in any “active risks view” when they can’t impact).

All identified risks brought up by the teams (e.g. at a ROAM session or similar) are registered.

Understanding risks: Resolved risks

Keep in mind when understanding risks that this is a different status to a closed risk – at least in SAFe methodology. Resolved risks should still be considered active in the PI they’re brought forward from and the resolution agreed upon at the ROAM session documented in your register. You can close the risks at the end of the PI if you’re certain they won’t have an impact in the future. 

If you have a lot of risks resolved right away – well done you! You’re very good at finding resolutions to your risks. This indicates a great decision-making ability at the ROAM sessions (or similar) and the ability to communicate and problem-solve across teams and management.

But consider this: You might have a very “authoritative” management team:

◉ Inclined to downplay the importance of the risks and deciding to close risks that the team might still find important but they’re not willing to disagree with management (e.g. the business owner).

◉ If many risks brought forward by the team are easily solved, perhaps the team (e.g. the product owner) should be given greater decision authority and more initiatives towards incubating a team empowerment culture could be beneficial. Especially if many of the risks brought forward are more akin to impediments or smaller dependencies with other teams – all of which the team should be able to handle itself.

Understanding risks: Owned risks

I’ve seen this term used interchangeably with Accepted in practice (disregard what labels are actually used in your organization for understanding risks).

Especially when risks are escalated to higher management levels and handling the risk requires larger commitments of resources or negotiations with other departments or vendors. Any actions taken are sometimes so far in the future and so little is actually done, that the risk might as well be considered Accepted from a team point of view. If risks are escalated, you’ll need to make sure the affected team(s) is sufficiently informed on the progress and that the owner is aware of (and decides accordingly in regard to) important deadlines in the risk. Anything completely dependent on an escalated risk not impacting, ought to be considered a stretch goal (i.e. something the team will work on but can’t commit to as achieving the goal is reliant on factors outside the team’s sphere of influence).  

A lot of Owned risks could also signify a lot of ambiguity – either regarding the delivery or how the context (e.g. surrounding organization) will impact the delivery. If the project or working on the product contains ambiguity in itself (e.g. a PoC), make sure that this is reflected in the expectations and the required level of detail and timespan in the planning for the team.

Understanding risks: Accepted risks

Accepted risks are actual concerns that people have about factors that might impede your product delivery, but the decision is to “not do anything” about it. In the majority of cases, there’s (hopefully) a very good reason for accepting the risk. As SAFe says: “Potential problems that must be understood and accepted.”

If there are risks, they’re reflecting conditions in your project no matter the probability or impact. When understanding risks, one risk might have a little impact on the project by itself but a large percentage of Accepted (and often forgotten thereafter) risks could have a compounded effect – even if it’s “just” in team members’ motivation as their concerns might be seen as neglected. I’ve seen risks accepted because they’re either too big or too small to be addressed. However, even smaller risks often have common themes hinting at deeper issues impeding your (short or long term) delivery, quality, employee motivation, etc.

Therefore, if you have a large backlog of “forgotten” risks you should take time out to periodically go through them with your management team to see what kind of decisions aren’t being made and why. For anyone familiar with ITIL this is akin to the problem management process – going through a lot of smaller incidents to see if there’s a common cause that should be resolved. If you’re able to spot common themes, then you could estimate an ROI by the compounded potential impact of the related risks. You can compare your decisions regarding risks with any other investment decision in improving your service and the supporting capabilities – some investments might even have a lower probability of ROI. At the very least you’ll want to set up reassessment conditions and a resulting prompt for each Accepted risk.

An important side note on Accepted risks

Depending on your risk management setup, your Accepted risks might be your “parking space” for active risks that are still relevant but, in practice, it doesn’t make sense to do anything about them (e.g. risks with an extremely low probability). Remember that a decision has been made for these risks = “won’t do anything – other stuff is more important.”

In so far as these risks might contribute to detecting common themes, there’s likely nothing to be gained from trying to make new decisions regarding any single one of the risks (unless some of the reassessment conditions have resulted in a prompt).

Ultimately, there’s a limited amount of decision-focus in any organization and it’s therefore very important that focus is prioritized.

Understanding risks: Mitigated risks

The most important factor in mitigated risks is that they progress. You’d definitely prefer to have your mitigating actions ready – or done – well before the estimated impact date.

You should be able to look at the latest date your risks are updated. If that date = creation date, you might have an issue. A bunch of things could be the cause of this (the lack of allocation, motivation to solve, or perceived importance being some). Look to see if the risk is assigned to the right person in regards to decision-making authority and/or skills, e.g. a mitigation plan which requires tasks to be done by resources across the team, products, or even other departments to be resolved might be difficult for a team member to progress sufficiently. Likewise, if the risk is escalated to someone outside the team, that person might have the needed decision authority and organizational pull but could lack the specialist knowledge to feel comfortable making decisions “before checking with XX” (this should be as short a process as possible – preferably 30 sec. as the person should be sitting right next to them.)

Even though a risk should have a single assignee who’s responsible, you’ll need to make sure that the right mix of competencies and decision authority is allocated to work on the risk. If the risk is escalated, the person assigned the risk should be working closely together with the right specialist/team member(s) = probably the one originally reporting the risk.

Risk velocity

Velocity = [time from inception] – [time to resolution or acceptance]. Try to keep your velocity as high as possible.

The longer a risk simmers in the backlog, the lower the likelihood of any action taking place. Unfortunately, this is not necessarily applicable to the probability or impact of the risk.

As a rule of thumb, risks that are not resolved by people in the project or release train within a set time limit (e.g. an iteration in SAFe) should be escalated to a level outside it.

Risk appetite

Your organization, project, release train, etc. all have implicit or explicit risk appetite which is a function of the size of the estimated impact, the impact date, and the velocity – “how fast do you make decisions regarding things that have a particular impact and how close do you like your close-calls.”

Some organizations have a very low official risk appetite, which might even be explicated in very detailed documentation of decision authority levels. However, in practice their risk appetite is extremely high as their low velocity (caused by lack of decision authority at the team level) results in impact by an unproportionate number of risks that might otherwise have been mitigated or avoided completely.

To re-iterate:

◉ A decision-empowered culture is, at all levels in an organization, very much a cultural thing. The reaction from management directly impacts how decision-prone the teams are. The more decision-prone teams generally perform better: higher motivation, better productivity, a steeper learning curve, etc.

◉ Management (and the rest of the organization) should trust that they have trustworthy, competent people working in the teams. Why? Because it is their responsibility to make sure the teams possess the knowledge, motivation, and tools required to do their job well.

Instead of trust, organizations are prone to implement control which is very inefficient – and even detrimental – in ensuring that complex tasks requiring high skill levels are done well.

I hope some of these pointers about understanding risks are applicable in your organization and perhaps can spark the conversation about how you manage risk or make decisions.

Source: itsm.tools.com

Wednesday, 9 February 2022

Difference between DMAIC and DMADV

DMAIC, DMADV, Six Sigma Exam Prep, Six Sigma Preparation, Six Sigma Guides, Six Sigma Skill, Six Sigma Jobs

1. DMAIC :

DMAIC is a part of the six sigma program which stands for Define, Measure, Analyze, Improve, and Control. DMAIC is a business strategy used to figure out how to improve processes while controlling costs.  It’s an effective way for identifying the root cause of significant problems within your operations or the surrounding environment and then leveraging that knowledge to create a plan to solve it.

1. Define : First make sure that you have an objective in mind for what you want to improve and understand the problem as much as possible; this will help determine which process is being improved.

2. Measure : Next establish a baseline from which you can measure improvement by collecting data before any changes are made. This might involve making a control chart or collecting data from past projects/work because it contains groups of similar problems.

3. Analyze : After you have accumulated the data, analyze it to see what you can do to improve and get a baseline figure. This is a good time to use Control Charts and Pareto charts to see what improvements are occurring and which ones need more improvement.

4. Improve : At this stage you should begin making changes that will improve your process. One of the most important factors is changing system thinking in terms of getting rid of bad habits and creating new good habits. This part of the DMAIC cycle is for continuous improvement in your company and overall health of the system.

5. Control : After you have made all of the improvements, look at the data again to see how much it has changed and if there are any fluctuations or trends in your data. This will show you if you need to do more or less of something that you implemented.

2. DMADV :

DMADV is a part of the six sigma program which stands for Definition, Measurement Design Analysis Verification. These are general tools in the design process that we have found can be helpful to learn more about what is going on with your project.

The five phases are  :

1. Definition : The definition stage is when you establish a common understanding of how the design will be performed.

2. Measurement : The measurement stage is when you collect data that helps you understand how your project is unfolding.

3. Design : The design stage is when you leverage all of the information collected in order to make wise decisions about the next steps you may take. The information that has been collected can be seen as an opportunity to drive the project to a better outcome rather than being viewed as a source of risk.

4. Analysis : The analysis stage is when you take all of the information collected in step 2 and step 3, and perform an analysis on it to help you understand what is really happening with your project.

5. Verification : The verification stage is when you compare expectations of how you want the project to unfold with how the project is actually unfolding. By doing this comparison, you are verifying that your original intentions are being met.

When to use ?

1. DMAIC : DMAIC methodology is used when the product has already been released out of the company, however there are issues or the product deviates from the customer’s demand.

2. DMADV : DMADV methodology is used when the product is not built and is currently in the designing & planning process. It is also used when the product could not be optimized and needs to be rebuilt.

Difference Between DMAIC and DMADV :

DMAIC DMADV 
DMAIC is about the improvement and control process. It defines the business process. Find problem then solve it in a target of providing improved solution.  The design and verification process involves the redesigning of the whole process to come close to the requirement described by the customer.
It addresses the current processes of the project.  It addresses the design processes of the projects. 
It works better with pre-existing projects.  It works better with new projects. 
It is about minimizing the processes and correcting the errors.  While it is about preventing errors. 
It uses quantitative tools.  It uses qualitative tools 
DMAIC are usually considered for short term projects.  DMADV are usually considered for long term projects. 
DMAIC gives specific solution.  DMADV is not the whole solution process, it is a part of the design solution. 
It is about correction.  It is about prevention. 
DMAIC controls future process performance.  DMADV verifies the design performance. 
It is initiated from a problem.  While it is initiated from an innovation solution. 

Source: geeksforgeeks.org

Friday, 4 February 2022

Why now is the time to coach your employees, and how to go about it

Prince2 Exam Prep, Prince2 Preparation, Prince2 Exam Prep, Prince2 Career, Prince2 Skills, Prince2 Job

You wouldn’t be alone in thinking that coaching an employee sounds time-consuming and, dare we say, tedious. After all, as a busy leader, you are tackling endless to-do lists daily, and coaching adds a sizable task to your already very full plate! But what if we told you that investing in coaching employees could help them to reach big goals, and achieve big goals for the company too!? Here is why taking the time to coach employees is worthwhile, and how to go about it…

What employee coaching looks like

Employee coaching will differ greatly depending on the role of the employee. However, all coaching shares an end goal of upskilled staff who hone their expertise and better understand the value of their position within the company and its objectives. Coaching requires leaders to steer and drive results, and the employee to demonstrate commitment to advancing in their role.

Essentially, employee coaching will set out:

◉ A coaching topic or area

◉ An action plan

◉ A defined timeline

◉ And the expected results

Collaboratively creating a coaching template may form part of your employee’s one-to-one. It is a great way of establishing long-term and short-term goals which encourage team members to strengthen their performance.

Coaching could take the form of regular conversations and quick check-ins to offer tips and guidance. Or perhaps you opt for less frequent but more involved coaching sessions to deep dive into a topic. It could be that an employee shadows you or another team member to gain experience. Or maybe you opt to undergo more formal training on an accredited professional development course. Whatever it looks like in your company, coaching helps employees to improve and grow, and, in fact, offering guidance can be of benefit to leaders too – more on that later!

A mutually beneficial arrangement

When it comes to creating opportunities for your employees to succeed, don’t forget to spare a thought for the company’s goals and objectives too. Whilst personal development is just that – a personal journey, the paths your team members take are going to have an impact on the business too. And so, you must look to achieve a programme of coaching which is mutually beneficial.

For example, you may establish that a better understanding of AI technology is a common wishlist item for your employees. If you feel this is beneficial for an upcoming tech project, then why not explore corporate training options for your project teams to learn and develop collectively? Our sister site, ILX group, offers some fantastic corporate training solutions.

Prince2 Exam Prep, Prince2 Preparation, Prince2 Exam Prep, Prince2 Career, Prince2 Skills, Prince2 Job
From the business’ standpoint, coaching offers a solution for gaining more talented, proficient staff at a fraction of the cost of hiring new talent. Coaching can drive results and inspire positive change within your organisation. It can aid retention as staff feel valued, and coaching can even drive innovation. As employees approach new topic areas and skills with interest and enthusiasm, it can spark ideas for improved ways of working.

Coaching has the power to bring teams together, boost morale, motivation and productivity, as well as clue your team up in a new area. Employees benefit from encouragement and direction towards reaching their full potential, and businesses gain upskilled staff who are equipped to contribute valuable work to the organisation.

Coaching builds better leaders

As a manager, it is within your remit to form a coaching action plan, to consistently monitor progress, and provide employees with the tools and resources they need to succeed. But in turn, you may just become a better leader too! Coaching puts you more in touch with your employees and builds positive working relationships. It helps staff to stop viewing you as a ‘boss’ and start seeing you as a leader, someone they can come to with complex problems, and work alongside to find solutions.

Without a doubt, you will refine and develop your skills as a coach – a fantastic addition to your CV! Beyond this, you could even opt to learn a brand-new skill alongside your employees. So establish your involvement, get to know your team better, and channel their motivation into progression and results. You may learn something new on the journey!

Source: prince2.com

Wednesday, 2 February 2022

Difference between DevOpS and ITIL

DevOpS and ITIL, ITIL, ITIL Certification, ITIL Exam, ITIL 4, DevOps

There are  lots of different opinions about DevOps and ITIL. In IT sector you have to choose one between them. DevOpS and ITIL have there own benefits but there mix approach bering most benefits to the table. DevOpS work really smooth with lean and Agile. DevOpS create it’s own feedback so defects can be corrected while working on new project or components.

1. What is DevOpS?

DevOpS main concept is collaboration, share goals and open communication means it’s complete the gap between development and operation. It’s collaborate between IT team, developer and tester which helps to production faster.

- DevOps implements some following practices:

- Continuous Development

- Continuous Integration

- Continuous Testing

- Continuous Monitoring

- Continuous Delivery

- Continuous Deployment

2. What is ITIL?

ITIL stands for Information Technology Infrastructure Library. It’s actually used to guide the it team to improve the value of service by focusing on solving business issue and creating business value. One of the important part of ITIL the configuration management database which provide services, users, software, hardware, documents and IT components to the central authority. ITIL has been adopted by thousands of organizations worldwide like Microsoft, NASA and HSBC. ITIL current version which is use in market is ITIL4,its provide a practical and flexible basis to support organizations for a digital transformation.  

Misconceptions about DevOps vs. ITIL :

1. DevOps can replace ITIL : There are essential business functions like service Management, support, operation, governance, costing these process are important and they both given by DevOpS and ITIL , only DevOpS or ITIL can’t provide it.

2. ITIL is always documentation : It’s actually not a true information ITIL is what the team make the choice the rules are made by team , ITIL is have It’s some own guidelines but the decision is always made by the IT team.

3. ITIL is only for large companies : It’s true that ITIL is used by large enterprises but It’s guideline can also benefit small business, small business are only need to know how to handle change management, major incident and knowledge management.

Use cases for DevOps and ITIL :

IT needs both ITIL and DevOpS elements.

DevOpS is a automated development , collaboration and blame-free culture.

It’s better collaboration between IT and business when we use ITIL and DevOpS together and it’s also helps in customer satisfaction due to the improved delivery of services and better management of issues. ITIL provides a tried-and-true starting point, where DevOps can add improvement with blameless examination, automation, other collaboratively approaches which makes every IT process easier.

Difference between DevOpS and ITIL :

DevOps ITIL 
DevOps refers to an effective collaboration between the development team and operations team.  ITIL refers to a set of detailed guidelines for effective and efficient management of organization’s IT services.
Use a methodical approach to minimize the friction between two teams.  Its use a systematic approach to manage the IT service to ensure the growth. 
CI and CD is the backbone of modern DevOpS philosophy.  ITIL aims to increase the delivery process. 
Continuous integration and continuous delivery are critical to increase.  Services are built, discuss, tested and implemented. 
DevOpS focus on concept. It has a dynamic body of knowledge.  DevOpS focus on concept. It has a dynamic body of knowledge. ITIL focus on development. It has a static body of knowledge. 

Source: geeksforgeeks.org